Spring-Mews-1

Development Programme

The current development timeline is as follows:

  

Planning approval

May 2012

Commencement of soft strip and demolition

Early September 2012

Demolition completed

December 2012

Start of piling works

February 2013

 Main Contractor on site

 15th April 2013

Completion

September 2014 

  

The Spring Mews development site became vacant in August 2012 as Vauxhall Gardens Community Centre moved into their temporary facility at 5 Glasshouse Walk. Over the past 5 months, demolition was completed in December and piling commenced in February and will continue into May 2013.  CLS would like to thank all our neighbours for their patience during the demolition phase.

 

 Picture1Picture2

 

 

 Picture3Picture4

 

 

 Picture5Picture6

 

What is happening now?

The piling has been completed by Cementation Skanska. CLS have now appointed Shepherd Construction Ltd as the Main Contractor to build the entire scheme. Work started on 15th April and the basement dig is well underway. The first tower crane has been installed on site to commence the construction of the cores.

  

Terra Firma have completed the bore holes to undertake investigations for the ground source heat pumps. 2 rounds of tests have been taken so far the outputs are looking positive.

  

 What will I see happening on-site in June/July/August?

  • Completion of the basement dig out. This will cover a large portion of the site
  • Erection of 2 tower cranes to commence the construction on the cores.
  • Replacement of the hoarding around the site.

 Programme of noisy works

 

Piling: 25th February to 6th May 2013

 

 

For further information please contact Muireann O’Donnell on 020 7840 7722 or email This e-mail address is being protected from spambots. You need JavaScript enabled to view it